What Is a Pre-Startup Safety Review (PSSR)?
A pre-startup safety review (PSSR) is a documented readiness review performed before an affected process is introduced to hazardous chemicals or returned to service after a covered change. It checks that the agreed prerequisites for the startup scope have been addressed; it is not, by itself, proof that every safety requirement has been met.
Answer first
A PSSR connects startup authorization to documented readiness.
For a functional-safety project, the review should make it clear which startup conditions, open items, procedures, training, testing evidence, and approvals are required before the process is placed into the intended operating state. The exact scope depends on the process, the change, the hazards, and the organization’s approved management system.
Purpose and timing
Review the readiness of the work, not only the equipment.
A PSSR is most useful when its criteria are set early enough that gaps can be resolved before startup pressure builds. OSHA’s process safety management standard includes PSSR requirements for covered processes; applicability and the required review method must be determined by the organization and its legal or compliance advisors.
For a project involving safety instrumented functions, the startup decision may depend on more than installed hardware. It can also depend on approved requirements, controlled configuration, test records, operating and maintenance procedures, training, alarm and bypass controls, and disposition of relevant action items.
Commissioning activities produce evidence. A PSSR reviews whether the relevant evidence and other prerequisites are adequate for the specific startup decision. Neither activity should be assumed to replace the other.
Functional-safety relevance
A PSSR should not overstate what it verifies about a safety function.
Confirm the approved basis is available.
The review can check whether the applicable safety requirements, operating limits, procedures, and change documentation are available to the people who need them.
Confirm what testing supports startup.
Commissioning, loop checks, configuration checks, validation activities, and field testing should be traceable to the approved project scope and any defined acceptance criteria.
Make residual items visible.
Items that remain open should be assessed, assigned, and controlled through the approved process; a signature should not hide unresolved startup risk.
What to review
Use a scoped, evidence-based review.
The project’s approved PSSR procedure controls the actual checklist and authority. In a functional-safety context, useful questions often include:
- Has the startup scope been defined, including affected equipment, operating modes, and interfaces?
- Are applicable procedures, training, emergency actions, and bypass controls ready for the intended operation?
- Is the identified testing and commissioning evidence available, reviewed, and traceable to the requirements basis?
- Have safety-relevant changes and open recommendations been evaluated through the approved change and action-tracking process?
Source use
Standards, guidance, regulation, and Mangan recommendations are not interchangeable.
IEC 61511 provides a lifecycle framework for process-industry functional safety; the applicable edition and project scope govern its use.
ISA-84 materials and project procedures can help teams apply lifecycle roles, evidence, and review practices in context.
OSHA PSM PSSR requirements apply only where the U.S. regulation and covered-process scope are met.
Use a controlled startup-readiness review that makes evidence, scope limits, owners, and unresolved actions explicit; do not treat it as a compliance or performance guarantee.
Common questions
PSSR questions in a functional-safety project
Is a PSSR the same as commissioning?
No. Commissioning produces and reviews implementation evidence; a PSSR is a documented readiness review for a defined startup decision. The project must determine what evidence is required.
Can a PSSR be a simple sign-off?
A checklist can support the review, but the process should make the defined scope, evidence, outstanding items, authorities, and disposition of concerns clear.
Does completing a PSSR prove compliance or safety?
No. It is one lifecycle control. Compliance, risk, and performance conclusions require the applicable legal, project, standards, and engineering evidence.
Need startup-readiness support?
Discuss the evidence, controls, and field work behind the startup decision.
Contact Mangan SISDownloadable term reference
Download: Pre-Startup Safety Review (PSSR) — Functional Safety Glossary PDF
Save or share this term-specific reference, including the answer-first definition, engineering review considerations, and primary-source references.
Download the Pre-Startup Safety Review (PSSR) PDF